4.1.3.1 Project Charter The project charter is the document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities. It documents the business needs, assumptions, constraints, the understanding of the customer’s needs and high-level requirements, and the new product, service, or result that it is intended to satisfy, such as:Project purpose or justification, Measurable project objectives and related success criteria, High-level requirements, Assumptions and constraints, High-level project description and boundaries, High-level risks, Summary milestone schedule, Summary budget, Stakeholder list, Project approval requirements (i.e., what constitutes project success, who decides the project is successful, and who signs off on the project), Assigned project manager, responsibility, and authority level, and Name and authority of the sponsor or other person(s) authorizing the project charter. Process: 7.1 Plan Cost ManagementDefinition: The process that establishes the policies, procedures, and documentation for planning, managing, expending, and controlling project costs.Key Benefit: The key benefit of this process is that it provides guidance and direction on how the project costs will be managed throughout the project.Inputs 1. Project management plan 2. Project charter 3. Enterprise environmental factors 4. Organizational process assets Tools & Techniques 1. Expert judgment 2. Analytical techniques 3. Meetings Outputs Cost management plan
4.1.3.1 Project Charter
The project charter is the document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities. It documents the business needs, assumptions, constraints, the understanding of the customer’s needs and high-level requirements, and the new product, service, or result that it is intended to satisfy, such as:
Project purpose or justification,
Measurable project objectives and related success criteria,
High-level requirements,
Assumptions and constraints,
High-level project description and boundaries,
High-level risks,
Summary milestone schedule,
Summary budget,
Stakeholder list,
Project approval requirements (i.e., what constitutes project success, who decides the project is successful, and who signs off on the project),
Assigned project manager, responsibility, and authority level, and
Name and authority of the sponsor or other person(s) authorizing the project charter.
Process: 7.1 Plan Cost Management
Definition: The process that establishes the policies, procedures, and documentation for planning, managing, expending, and controlling project costs.
Key Benefit: The key benefit of this process is that it provides guidance and direction on how the project costs will be managed throughout the project.
Inputs
1. Project management plan
2. Project charter
3. Enterprise environmental factors
4. Organizational process assets
Tools & Techniques
1. Expert judgment
2. Analytical techniques
3. Meetings
Outputs
Cost management plan